Technical specifications

Scope of works:

  • 1 two-lane road tunnel and 1 bridge
  • total tunnel length 100 m 
  • length of the total section to be built by us under the contract: approx. 520 m

Construction method

  • Cut and cover method 
  • Crossing of the A 3 motorway in 10 construction phases without interrupting the traffic flow
  • Crossing of an existing tunnel on the Cologne-Frankfurt high-speed railway line

Geology

  • alternating sequences of sand and gravel

General data

Project
LSG Betriebsweg Gateway Gardens

Client
Grundstücksgesellschaft Gateway Gardens

Contractor
Wayss & Freytag Ingenieurbau AG

Construction time
01/2019-12/2023

Construction sum net
€  14 million

 

Utilisation
Infrastructure
Type
Road tunnel to give LSG caterers access to the Frankfurt Airport apron
Length
100 m
Construction Method
cut and cover method
Related Projects

Related Projects

Tunnel Vötting
Tunnel Vötting
Germany

95 m preliminary cut, preliminary cut approx. 35,000 m³ 30 m north portal structure 462 m tunnel constructed by the mining method: Top heading and bench/invert heading in Tertiary hilly terrain

Read more
Neu-Isenburg Junction,
Neu-Isenburg Junction,
Germany

single-track railway tunnel with a widened section allowing the railway line to be split into 2 tracks, 14 trough blocks, 13 tunnel blocks, total length 353 m.

Read more
Bad Cannstatt Tunnel
Bad Cannstatt Tunnel
Germany

6 km railway tunnel from Stuttgart central railway station to Bad Cannstatt as part of the large-scale project „Stuttgart 21“.

Read more